By Nawara Fattahova
KUWAIT: The ministry of public works is continuing to execute road projects, especially during the partial curfew hours, to finish more work as the roads are almost empty. Kuwait Times went on a tour of some roads under construction on Saturday night.
At the Seventh Ring Road, workers were applying a layer of asphalt. Jarrah Al-Harbi, director of engineers developing the Seventh Ring Road project, said the team was working on laying 1,300 tons of asphalt over an area of three kilometers, comprising of three lanes.
"We work from 2:00 pm till 8:00 pm daily on this project that includes construction works and services, in addition to asphalt works. We work different timings including the day and night," he told Kuwait Times.